GCR Mongolia Shaft 4 Stage Installation

GCR Mongolia recently completed a very significant task: the installation of the stage into shaft 4 on the Oyu Tolgoi Project. This was the first major mechanical task in completing the infrastructure required to execute the shaft sinking works that will commence in February 2020. The works will progress down to a depth of just over 1100m over the next 18 months.

The overall Oyu Tolgoi Project is already an operational gold mine located in the southern Gobi Desert of Mongolia, approximately 550 kilometres south of the capital, Ulaanbaatar. GCR Mongolia’s contract for Shaft 3 & 4 sinking includes the construction of two shafts that will provide additional air ventilation into the existing tunnels of the operating mine. The increase in air will allow for an expansion of the underground mining operation for future production. After a process of concrete lining, the shafts will be 10m and 11m in diameter respectively.

Site establishment commenced last October and GRC Mongolia started with civils and construction of the pre-sink, which is the initial part of the shaft they have lowered the stage into. Since June this year, the team has been busy erecting the structure of the headframe and buildings for services that support the sinking works. Both facilities, nearly 800m apart, are designed and constructed to facilitate execution during the winter months when temperatures drop to -40 degrees Celsius .

The stage is 25m in length and comprises of five decks with the fifth deck being a floating (movable) deck, where most of the shaft work will be completed. When the floating deck is fully extended, the total length is 31m, weighing 212 tonnes. This lift was preceded by a load test of 325 tonne to attain approval for using the crane and its rigging, the largest lift ever conducted at Oyu Tolgoi site.

Greg Kember, Project Director GCR, said it has been a challenging but enjoyable journey so far after the team commenced work on the contract for the Oyu Tolgoi Project in Mongolia 15 months ago.

“Our engineering and procurement efforts have combined worldwide resources and culminated with our design team operating from our Ulaanbaatar office,” he said.

“Our team, with over 1100 individuals, has done an absolutely amazing job communicating and coordinating their respective works to achieve these tasks safely and on schedule. Now we turn our attention to the remainder of the lifts and E&I commissioning activities.”

 

Share this article:
Subscribe to our news

Connect With Us

LinkedIn

✖️ Did you know? ✖️

At the time of construction, the Cape Lambert Jetty was the longest jetty in the world, and one of the highest. The jetty measured in at 2.3km in length and was built 18m in height above sea level because of the prevalence of cyclones in the region. It was built using A-frame steel piles, which many remarked looked like matchsticks. For the high standard of work on the Cape Lambert Marine Facility, the Harbourworks Clough Joint Venture was awarded the prestigious Australian Federation of Construction Contractors Construction Achievement Award in 1973.